选择题:项目经理在运行预算方案编制时,收集到的基础数据如下:工作包的成本估算为40万元;工作包的应急 题目分类:软考高级 题目类型:选择题 查看权限:VIP 题目内容: 项目经理在运行预算方案编制时,收集到的基础数据如下:工作包的成本估算为40万元;工作包的应急储备金为4万元,管理储备金为2万元。该项目的成本基准是()万元。A.40B.44C.42D.46 参考答案: