选择题:● 在某工程网络计划执行过程中,如果某项非关键工作实际进度拖延的时间超过其总时差,则(69) 。 (69

  • 题目分类:软考中级
  • 题目类型:选择题
  • 查看权限:VIP
题目内容:
● 在某工程网络计划执行过程中,如果某项非关键工作实际进度拖延的时间超过其总时差,则(69) 。

(69)

A.网络计划的计算工期不会改变

B.该项工作的总时差不变

C.该项工作的自由时差不变

D.网络计划中关键线路改变




参考答案:

● 《计算机软件保护条例》规定:对于在委托开发软件活动中,委托者与受委托者没有签订书面协议,或者

● 《计算机软件保护条例》规定:对于在委托开发软件活动中,委托者与受委托者没有签订书面协议,或者

查看答案

● Which of the following elements can be called the key element of a computer?(71) (71)A.p

● Which of the following elements can be called the key element of a computer?(71) (71)A.p

查看答案

● The (72) has several major components, including the system kernel, a memory management

● The (72) has several major components, including the system kernel, a memory management

查看答案

● Which of the following is not part of the quality assurance process?(73) (73)A.Operation

● Which of the following is not part of the quality assurance process?(73) (73)A.Operation

查看答案

● Which of the following is not part of a modern quality management concept?(74) (74)A.Per

● Which of the following is not part of a modern quality management concept?(74) (74)A.Per

查看答案