Creating WBS means subdividing the major project deliverables into smaller components until the deliverables are defined to the ( ) level.
A.independent resource
B.individual work loaD
C.work milestone
D.work package
参考答案:
答案解析:
Creating WBS means subdividing the major project deliverables into smaller components until the deliverables are defined to the ( ) level.
A.independent resource
B.individual work loaD
C.work milestone
D.work package