题目内容:
● The Estimate Activity Resource process is closely coordinated with the (73)process.
(73)
A. Estimate Costs
B. Sequence Activities
C. Plan Communications
D. Conduct Procurements
参考答案:
● The Estimate Activity Resource process is closely coordinated with the (73)process.
(73)
A. Estimate Costs
B. Sequence Activities
C. Plan Communications
D. Conduct Procurements