题目内容:
A project manager believes that modifying the scope of the project may provideadded value service for the customer.The project manager should()
A.assign change tasks to project members
B.call a meeting of the configuration control board
C.change the scope baseline
D.postpone the modification until a separate enhancement project is funded after this project is completed according to the original baseline
参考答案:
答案解析: