题目内容:
项目被估算的成本是$1.5百万,进度维持六个月时间,在三个月之后,挣值分析显示下面情况:EV=$650,000;PV=$750,000;AC=$800,000,进度和成本偏差各是多少?( )
A.SV=+$100,000/CV=+$150,000 B.SV=+$150,000/CV=-$100,000
C.SV=-$50,000/CV=+$150,000
D.SV=-$100,000/CV=-$150,000
参考答案:
答案解析: